Rules that keep Azure Boards trustworthy enough to plan with. If the board does not match reality, sprint metrics are fiction.

Work item hierarchy

Level Type Size Owner
1 Epic a quarter or more; one business outcome Product Owner
2 Feature 1–3 sprints; independently releasable Product Owner + lead
3 User Story / Bug ≤ 8 points; fits in one sprint team
4 Task ≤ 1 day; optional, for the team's own tracking engineer

Rules: every Story and Bug has a parent Feature; every Feature has a parent Epic. KTLO work hangs under a standing Epic per quarter, KTLO 2026-Q4, with Features per service (KTLO checkout, KTLO payments-gateway, ...), so it is visible in the same roadmap as feature work. Incident follow-ups are Bugs or Stories linked to the incident number in the title ([INC-1042] Add pool exhaustion alert).

States

State Meaning Entry rule
New captured, not refined anyone
Ready meets DoR refined, estimated
Active someone is working on it now assigned; WIP ≤ 2 per engineer
In Review PR open PR linked
Resolved merged and deployed, awaiting acceptance deployment run linked
Closed meets DoD, accepted PO acceptance
Removed will not do reason in discussion

Items do not skip states backward silently: moving Active → Ready requires a discussion comment.

Area and iteration paths

Area:       IncidentOps
            IncidentOps\API
            IncidentOps\Web
            IncidentOps\Functions
            IncidentOps\Insights
            IncidentOps\Platform        (infra, pipelines, standards)

Iteration:  IncidentOps\2026\Q4\Sprint 20   (2 weeks, Monday to Friday of week 2)

Area path = owning component. Iteration path = sprint committed in. Unplanned work entering mid-sprint keeps the sprint iteration and gets the unplanned tag.

Tags

Tag Use Feeds
ktlo keep-the-lights-on: maintenance, upgrades, operational fixes KTLO vs feature split
toil manual, repetitive, automatable operational work toil %
tech-debt deliberate improvement of code or architecture debt allocation
incident-followup action item from a postmortem retrospective actions
retro-action action item from a sprint retrospective retrospective actions
risk, dependency item tracked in the risk and dependency log weekly risk review
unplanned entered after sprint start say/do, interrupt rate
security vulnerability or hardening compliance reporting
blocked waiting on someone outside the team; reason in discussion standup, risk log

No other tags without a team decision; free-form tags make queries useless.

Required fields

Field Story/Bug Feature
Area path, iteration path ✔ ✔
Parent ✔ ✔
Story points ✔ —
Acceptance criteria ✔ ✔ (success metric)
Severity (Bug) ✔ —
Target date — ✔
Value area (Business / Architectural) ✔ ✔

Backlog readiness

  • Target: 1.5 sprints of Ready stories ranked at the top of the backlog.
  • No item older than 90 days in New: weekly sweep closes or refines it.
  • Bugs triaged within 2 business days of creation: severity, area, priority set.

Capacity planning

Capacity is set per sprint in the Capacity tab before planning.

Input Value
Sprint length 10 working days
Focus hours per engineer per day 6
On-call primary 50% capacity that week (interrupt-driven)
On-call secondary 80% capacity
PTO and holidays from the team calendar
Allocation 60% features, 25% KTLO, 15% tech debt (see KTLO vs roadmap)

Plan to 80% of computed capacity. The remaining 20% absorbs unplanned work; if it is not used, pull from the top of the Ready backlog.

Worked example, 6 engineers, one with 3 days PTO, one primary and one secondary on call:

Base               6 × 10 days × 6 h            = 360 h
PTO                3 days × 6 h                  = −18 h
On-call primary    1 × 10 × 6 × 50%              = −30 h
On-call secondary  1 × 10 × 6 × 20%              = −12 h
Available                                          300 h
Plan to 80%                                        240 h
  Features 60%   144 h   KTLO 25%   60 h   Debt 15%   36 h

Sprint predictability metrics

Metric Definition Target Source
Say/do ratio points Closed in sprint that were committed at planning ÷ points committed 80–95% (above 95% suggests sandbagging) Sprint burndown, committed scope snapshot
Velocity stability coefficient of variation of the last 6 sprints' completed points < 20% Velocity report
Unplanned rate points tagged unplanned ÷ points completed < 20% query below
Carry-over items moved to next sprint ÷ items committed < 15% iteration history
Cycle time Active → Closed, p50 and p85 p85 ≤ 5 days for stories Cycle time widget
WIP Active items per engineer ≤ 2 board
Allocation actual vs planned completed points by tag group ÷ completed points within ±5 pp of plan query below

Reported in the sprint review and in the weekly stakeholder update. A say/do below 80% two sprints running triggers a retro topic on planning, not a push to work harder.

Weekly hygiene sweep

15 minutes, lead and Scrum Master, every Thursday:

  1. Active items without an update for 3 days.
  2. Items in In Review with no linked PR, or Resolved without a deployment run.
  3. Stories without parent, area path or estimate.
  4. blocked items: blocker still valid? owner? date?
  5. Bugs untriaged older than 2 business days.
  6. New items older than 90 days.

Queries

WIQL for the shared queries the sweep and metrics use.

Orphan stories and bugs:

SELECT [System.Id], [System.Title], [System.State]
FROM WorkItemLinks
WHERE ([Source].[System.TeamProject] = @project
  AND [Source].[System.WorkItemType] IN ('User Story', 'Bug')
  AND [Source].[System.State] <> 'Removed')
  AND ([System.Links.LinkType] = 'System.LinkTypes.Hierarchy-Reverse')
  AND ([Target].[System.WorkItemType] = 'Feature')
MODE (DoesNotContain)

Unplanned work in the current sprint:

SELECT [System.Id], [System.Title], [Microsoft.VSTS.Scheduling.StoryPoints]
FROM WorkItems
WHERE [System.TeamProject] = @project
  AND [System.IterationPath] = @currentIteration('[IncidentOps]\IncidentOps Team')
  AND [System.Tags] CONTAINS 'unplanned'

Allocation split completed this sprint:

SELECT [System.Id], [System.Tags], [Microsoft.VSTS.Scheduling.StoryPoints]
FROM WorkItems
WHERE [System.TeamProject] = @project
  AND [System.IterationPath] = @currentIteration('[IncidentOps]\IncidentOps Team')
  AND [System.State] = 'Closed'
  AND [System.WorkItemType] IN ('User Story', 'Bug')

Group by tag (ktlo, tech-debt, none = feature) in the Analytics view or a pivot.